Lake City Utilities - Columbia High School
Lake City Distribution/Collections Department needed to extend water mains serving Columbia High School to loop and provide additional water and fire flow. The improvements consist of an internal 8 inch extension of from the stadium south approx 1,800 ft, an 8 inch water main extended from the B&B Store along 252 with a directional bore and onto the school property onto the existing loop. The system also proposes fire hydrants. To facilitate the project, Gmuer Engineering completed a sUAS (Drone) aerial of the project limits to save survey costs, utiltized historical SRWMD Permit Drawings to save on soft dig costs to the City, permitted the water improvements with FDEP, supply the schematic utility plans for construction, review record drawings and as-builts.