City of Newberry SW Water Main Extension

The City of Newberry planned a water main extension in southwest Newberry to loop and backfeed a large portion of the City’s service area. The route and pipe sizes generally consists of 2,100 LF of 12” Watermain aligned with SW 15th Ave between SW 260th ST and west to SW 266th St, 4,100 LF of 12” watermain aligned along the eastern wide of CR337 / SW 266th St north to Newberry Rd and south to SW 18th Road, and 500 LF of 8” Watermain aligned with SW 264th ST from the proposed 12” along the SW 15th Ave alignment north to the current termination of SW 264th ST. To facilitate the project, Gmuer Engineering designed the utility construction plans, permited the water and wastewater improvements with FDEP, permitted the ROW Use and potential water main crossing of CR337 with Alachua County and SR26 with FDOT, supplied utility construction plans for construction, reviewed record drawings and as-built surveys, and certified testing results witnessed by the City.